An algorithmic review of the technological progress and milestones in resource-constrained project planning
Permanent lenke
https://hdl.handle.net/10037/36059Dato
2024-12-30Type
Journal articleTidsskriftartikkel
Peer reviewed
Sammendrag
Engineering, procurement, and construction projects are time-intensive and
subject to resource constraints. Modern project planning software requires
optimization algorithms to schedule tasks while considering resource availability. A comprehensive review of the optimization algorithms used in project
planning has not yet been conducted. This study seeks to bridge the gap
through an algorithmic review of the Resource-constrained Project Scheduling Problems (RCPSPs) literature and investigates the following research
questions: What are the milestones on the main development trajectory of
optimization algorithms for solving RCPSPs? How might this influence future
advancements in the field? To answer these questions, the Main Path Analysis
(MPA) method is employed to review the development trajectory and milestones from over 1100 project scheduling articles published between 1980
and 2024. Cluster Analysis (CA) complements the investigations by identifying the prevalent research themes, mathematical features, and solution algorithms. Recommendations for future research directions, supported by the
systematic review, conclude the study. This review provides a reference for
project management researchers focused on industrial applications of project
scheduling problems.